Construction Update

November 10, 2016

The pavement markings have been installed this week and the railroad crossing has been reconstructed. Sewalls Falls Road is now open to two-way traffic.

 

Project Schedule

March 2014

NEPA Approval

September 2014

Begin Final Design

May 21, 2015

Advertise for Construction

July 15, 2015

Project Award

July 20, 2015

Notice to Proceed

August 3, 2015

Begin Construction

November 10, 2016

Bridge Open

 

Project Contacts

Ed Roberge, P.E.
Concord City Engineer
603.225.8520 eroberge@concordnh.gov

Gene McCarthy, P.E.
McFarland Johnson Project Manager
603.225.2978
gmccarthy@mjinc.com

Bridge Update from Concord TV!