Construction Update

September 15, 2016

This past week’s construction activities included completing setting and tying reinforcing for the bridge deck, sidewalk, and brush curb, setting up equipment to be used when they place concrete for the bridge deck (See Photo), completing the installation of drainage for the project, and continued progress on the construction of the approach roadways. Next week’s activities will include placing concrete for the bridge deck, continued construction of the approach roadways, forming and placing concrete for the approach slab on the South side, and the completion of the gas main on the North side of the project.

 

Project Schedule

March 2014

NEPA Approval

September 2014

Begin Final Design

December 2014

Finalize Permits

May 21, 2015

Advertise for Construction

July 15, 2015

Project Award

July 20, 2015

Notice to Proceed

August 3, 2015

Begin Construction

 

Project Contacts

Ed Roberge, P.E.
Concord City Engineer
603.225.8520 eroberge@concordnh.gov

Gene McCarthy, P.E.
McFarland Johnson Project Manager
603.225.2978
gmccarthy@mjinc.com

Watch the Bridge Demolition!