Construction Update

October 21, 2016

The past week’s activities have included the completion of the bridge and roadway guardrail (See Photo’s), preparing the sidewalk areas for pavement, hydro seeding within the project limits, cleaning up the site of construction debris and preparing the concrete bridge deck for pavement. Next week it is anticipated that the bridge deck and sidewalks will be paved, the roadway will be striped, the vegetated swale adjacent to the NH Fish and Game parking area will be worked on, and clean up of construction debris within the project limits will continue.


Project Schedule

March 2014

NEPA Approval

September 2014

Begin Final Design

December 2014

Finalize Permits

May 21, 2015

Advertise for Construction

July 15, 2015

Project Award

July 20, 2015

Notice to Proceed

August 3, 2015

Begin Construction


Project Contacts

Ed Roberge, P.E.
Concord City Engineer

Gene McCarthy, P.E.
McFarland Johnson Project Manager

Bridge Update from Concord TV!